Integrated Solutions – Tunnel construction and immersion

Challenge

Our client, Ballast Nedam, required the safe movement and precise positioning of ten concrete tunnel elements, each weighing approximately 47,000 tonnes, from a flooded precast construction dock to their final locations in the Khor Al-Zubair channel for controlled immersion. The tunnel will enable road traffic to cross the channel as part of a newly constructed route linking Al Faw Port, at Iraq’s southernmost tip, with Baghdad and onward to Turkey.

This operation involved highly complex heavy-lift logistics using floating pontoons and anchor systems in strong river currents, while also operating under restricted marine access conditions, as installation activities had to be carefully planned to minimise disruption on active shipping lanes.


Solution

Results and impact

  • All ten tunnel elements were safely and successfully; floated from the precast dock, winched to temporary mooring locations for fit-out, transported to their immersion locations and held steady on location whilst lowered accurately onto seabed supports and connected sequentially across the river.
  • Solutions-led approach to identifying and implementing continuous current monitoring, enabling safer operations and improved planning accuracy leading to installation efficiencies.
  • These activities were underpinned by our comprehensive equipment portfolio, supporting both topside operations and survey requirements.
  • Improved communication and safety alignment ensured operations met international safety standards despite challenging local conditions.
  • The project was delivered with safe execution within a live shipping environment with minimal closures.